|
The Challenge: This
customer had recently commissioned a parenteral filling facility
but had met with poor operations, confusing operator interface
for DCS control, lack of scalability, poor batch controls,
and major sterility issues. The poor design resulted in extended
manufacturing cycles that reduced plant capacity and operability
to unacceptably low levels. Although brand new, the plant
needed a major overhaul to the Automation and Equipment Systems
and they needed it in a hurry in order to meet scheduled
production requirements.
The Solution: CHT’s
Subject Matter Expert Engineer worked with the manufacturing
department to operate the facility for data gathering purposes.
Information was obtained that enabled a Failure Mode Effects
Analysis determining the root causes of the process and controls
problems. The solution proposed by CHT and which was agreed
was to make several minor but critical equipment improvements
and then to operate the plant to make sufficient product inventory
to permit a brief shut down.
While this was happening, CHT
led a team from all departments gaining consensus on the
fundamental changes required for a successful manufacturing
operation. CHT then developed Functional Specifications, participated
in the selection of other team members, and managed the project
through engineering and integration of the required modifications
required to resolve the fundamental causes of the operability
issues. Equipment and piping modifications were made and
a new S88 compliant batch control system (software, existing
hardware was utilized) was installed.
The timely construction
completion, quick commissioning, and immediate operation
objectives were met or exceeded and the customer was able
to successfully use the facility for filling the new product
for an international roll out.
The Result: The highly
motivated engineering and integration team worked superbly
together to produce a remarkable facility in record time
ultimately leading to the timely and successful product launch.
|